NEW ENGLAND HIGHWAY
UPGRADE (YARRAMAN
– TOOWOOMBA),
WIDEN PAVEMENT

COMMITTED TO EXCELLENCE.
SECTOR / DISCIPLINE
Roads and Infrastructure
LOCATION
New England Highway
between Cooyar and Bum Bum Creek
Darling Downs, Qld
DATE
January 2022
ASSET OWNER
Department of Transport and Main
Roads
CLIENT/DELIVERY AGENCY
Projex Partners
VALUE
$24.5m
PROJECT DESCRIPTION
The New England Highway widening project, spanning from Cooyar to Bum Bum Creek within Queensland’s Toowoomba Region, enhances road safety and optimises freight efficiency.
By expanding the road width and strength capacity, particularly for
B-doubles and heavy vehicles, the project boosts transport productivity and reliability.
The project additionally reduces travel time and maintenance costs,
ultimately fostering economic development in southern Queensland and the Darling Downs region.
JC CIVIL PROJECTS ROLE
JC Civil Projects was engaged by Projex Partners with the responsibility of delivering a comprehensive options and risk analysis for the options report. JC Civil Projects was tasked with providing detailed business case estimates and conducting thorough risk analysis.
This collaborative effort ensured a robust assessment of potential options and risks, providing a solid foundation for informed decision-making in the project’s development.

KEY DELIVERABLES
JC Civil Projects played a pivotal role in the options and risk analysis, which
included:
-
JC Civil Projects used first principles estimating and cost engineering, along with Expert Estimation software, to refine cost estimates. These estimates included direct costs, overhead, and resource calculations, while risk profiles were generated using @Risk software.
-
Employed Monte Carlo simulations for programming and scheduling purposes.
JC Civil Projects' role in the business case estimates and risk analysis involved:
-
Conducting first principles estimating and cost engineering using Expert Estimation - drafting and detailing cost estimates
-
Programming and scheduling through Monte Carlo simulations and Primavera P6 software.
KEY PROJECT HIGHLIGHTS
The project highlights included:
-
Widening and resurfacing the highway (new 10m-wide pavement at identified sections)
-
Drainage upgrades
-
Improvements to intersections between Cooyar and Bum Bum Creek, south of Yarraman.
OUTCOMES AND ACHIEVEMENTS
JC Civil Projects provided comprehensive options and risk analysis, enabling informed decision-making through thorough assessment and precise cost estimation, using first principles and innovative simulation techniques.